dc.contributor.advisor | Bratvold, Reidar | |
dc.contributor.author | Mohus, Erlend | |
dc.date.accessioned | 2018-10-03T13:51:12Z | |
dc.date.available | 2018-10-03T13:51:12Z | |
dc.date.issued | 2018-06 | |
dc.identifier.uri | http://hdl.handle.net/11250/2566243 | |
dc.description | Master's thesis in Industrial economics | nb_NO |
dc.description.abstract | It is a well-known fact that many projects on the Norwegian Continental Shelf (NCS) have been completed with cost overruns and schedule delays. Similar cost- and schedule deviations have been documented in other industries, leading professor Flyvbjerg of Oxford University to propose the following “iron law of megaprojects”: “Over budget, over time, over and over again”. Not surprisingly, such overruns are eroding the economic value of the investments. | nb_NO |
dc.language.iso | eng | nb_NO |
dc.publisher | University of Stavanger, Norway | nb_NO |
dc.relation.ispartofseries | Masteroppgave/UIS-TN-IØRP/2018; | |
dc.rights | Navngivelse 4.0 Internasjonal | * |
dc.rights.uri | http://creativecommons.org/licenses/by/4.0/deed.no | * |
dc.subject | industriell økonomi | nb_NO |
dc.subject | estimates | nb_NO |
dc.subject | overruns | nb_NO |
dc.subject | production | nb_NO |
dc.subject | bias | nb_NO |
dc.subject | value erosion | nb_NO |
dc.subject | reference class forecasting | nb_NO |
dc.subject | risikostyring | nb_NO |
dc.subject | finans | nb_NO |
dc.title | Over Budget, Over Time, and Reduced Revenue, Over and Over Again - An Analysis of the Norwegian Petroleum Industry's Inability to Forecast Production | nb_NO |
dc.type | Master thesis | nb_NO |
dc.subject.nsi | VDP::Samfunnsvitenskap: 200::Økonomi: 210 | nb_NO |